Industrial Engineering And Production Management most imp mcq
01. Work study is mainly aimed at
A.determining the most efficient method of performing a job
02. The type of organisation preferred for an automobile industry, is
A.line and staff organization
02. Product layout is used for
A.mass production
03. The bonus increases in proportion to the increase in efficiency. This statement applies to
A .Emerson's efficiency plan
04. Routing
A.prescribes the sequence of operations to be followed
05. A dummy activity becomes a critical activity when its
A. earliest start time (EST) is same as its latest finishing time (LFT).
06. The start or completion of task is called
A.an event
07. Service time in queuing theory is usually assumed to follow
A.exponential law
08. At the break even point,
A.total cost is equal to sales revenue
09. An activity of the project is graphically represented by an arrow on the
A. network diagram.
10. Earliest finish time can be regarded as
A.earliest start time + duration of activity
11. Time study is carried out to determine the time required to complete job by
A.an average worker
12. Slack may be
A. positive, zero or negative.
13. Generally PERT is preferred over CPM for the purpose of
A. project evaluation.
14. Product layout is also known as
A.synthetic layout
15. The work study is done by means of
C.stop watch
16. Break even analysis represents the relationship between
A. cost and volume.
17. CPM requires
A.single time estimate
18. Halsey plan of wage incentive
A.is applied to all level of workers
19. Which of the following wage incentive plan is applied to all workers?
A.Halsey plan
20. Actual performance of a task is called
A.an activity
21. The interchangeability can be achieved by
A.standardisation
22. The value engineering technique in which experts of the same rank assemble for product development is called
B.brain storming
23. Which one of the following techniques is used for determining allowances in time study?
D.Work sampling
24. Process layout is also known as
A.analytical layout
25. PERT is a
A. project planning and control technique.
26. Queuing theory is associated with
A.waiting time
27.PERT requires
A.triple time estimate
28.A-B-C analysis is based on
A. Pareto's principle.
29. In value engineering, the term value refers to
A.utility of the product
30. In inventory control theory, the economic order quantity is
A.optimum lot size
31. Production cost refers to prime cost plus
A.factory overheads
32. Military type of organisation is known as
A.line organisation
33. Fixed position layout is also known as
A.static product layout
34. Bar chart is suitable for
A.minor work
35. Which one of the following chart gives simultaneously information about the progress of work and machine loading?
A.Man-machine chart
36. PERT is an
A. event oriented technique.
37. The chart which gives an estimate about the amount of materials handling between various work stations is known as
A.travel chart
38. The type of organisation preferred for a steel industry, is
A.line, staff and functional organisation
39. A diagram showing the path followed by men and materials while performing a task is known as
A.flow diagram
40. Work study involves
A.method study and work measurement
41. A-B-C analysis is used in
A.inventory control
42. In order to avoid excessive multiplication of facilities, the layout preferred is
A.process layout
43. Simplex method is the method used for
A.linear programming
44. Dispatching
A.is concerned with the starting of processes
45. Job evaluation is the method of determining the
A.relative values of a job
46. Which of the following type of layout is suitable for automobile manufacturing concern?
A.product layout
47. Representative time is the average of times recorded by
A. work study man for an operation.
48. The aim of value engineering is to
A.minimise the cost without change in quality of the product
49. In time study, the rating factor is applied to determine
A.fixation of incentive rate
50. Gantt chart is used for
A.production schedule
51. CPM stands for
A.Critical Path Method
52. The average time recorded by work study man for an operation is called
A.representative time
53. In value engineering, important consideration is given to
A.cost reduction
54. Scheduling
A.determines the programme for the operations determines the programme for the operations
55. F. W. Taylor introduced a system of organisation known as
A.functional organisation
56. The correct sequence of phases in value engineering is
A.creative phase, information phase, investigation phase, evaluation phase
57. Micromotion study is
A.subdivision of an operation into therbligs and their analysis
58. Valve analysis is particularly of interest when
A.production is on large scale
59. The type of layout used for manufacturing steam turbines, is
A.fixed position layout
60. Gantt chart gives information about
A.production schedule
61. Gantt chart gives information about
A.production schedule
62. Merit rating is the method of determining the
A.worker's performance on a job
63. PERT stands for
A.Programme Evaluation and Review Technique
64. In Emerson's efficiency plan of wage incentive system, bonus is paid to a worker
A.whose output exceeds 67% efficiency
65. The production scheduling is simpler and high volume of output and high labour efficiency are achieved in the case of
A.product layout
66. Standard time is equal to
A.normal time plus allowances
67. An event is a function of
A. two or more activities.
68. The mathematical technique for finding the best use of limited resources of a company in the maximum manner is known as
C.linear programming
69. Break even analysis consists of
A. sales revenue
B. fixed expenses
C. variable cost
D.all of these
70. Slack represents the difference between the
A.earliest completion time and latest allowable time
71. Queuing theory is used for
A. inventory problems
B. traffic congestion studies
C. jobshop scheduling
D. all of these
72. Break even point is the point where
D.sales revenue and total expensive lines intersect
73. Dummy activities are used to
C.maintain the required net work
RELATED SEARCHES
ReplyDeleteindustrial engineering mcq with answers pdf
industrial engineering questions and answers pdf
industrial engineering and production management mcq
production engineering mcq
basic mechanical engineering mcq
industrial engineering quiz
mcq on production management
industrial management questions and answers pdf